Week 18 (2/19/17-2/25-17)

2/20 – Working at Trailer

  • Designed final battery box and and determined all materials needed for box
  • Determined lengths of receptacle wiring (#14) needed
  • Figured out method of grounding. Would ground inverter and charge controller at the front-most roof beam, because this is the most accessible piece of metal that is connected to the main trailer frame. Would use a self-drilling metal screw with a ring terminal crimped onto #8 green wire.
  • Determined length of grounding (#8) wire needed.

2/24 – Installation

  • Drilled holes in roof for front 2 panels. Inserted bolts and sealed holes
  • Installed wood frame for mounting of inverter and charge controller
  • Completed constructing battery box. Simply need to place in trailer with batteries, screw into floor, and screw in front board